STATUS OF RURAL ROAD CONSTRUCTION WORKS TAKEN UP UNDER PMGSY IN THE DISTRICT OF MALDA IS AS FOLLOWS:
1) Total completed road length (since inception) : 1304.769 KM
2) Total completed road length (since 2011) : 869.79 KM
Target of Financial Year 2019-20 : 125 KM, Completed : 125.41 KM
Target of Financial Year 2020-21 : 299.895 KM, Completed : 20 KM (Aug'20)
F Year | Work Name | Starting Date & Completion Date | Block Attached | Physical Achievement | Financial Achievement | No. of Beneficiary / inhabitant got benefitted under the scheme | Funding Department / Executing Agency | Current Status of the work |
---|---|---|---|---|---|---|---|---|
2018-19 | 18 Mile to Baishnabnagar - Package No. WB 11 242 | 01-04-2018 to 31-03-2019 | Kaliachak-III | 15% | 0 | ZP | Ongoing | |
2018-19 | SH connection (Churkadirpur) to NH 34 Bypass connection - Package No. WB 11-249 | 01-04-2018 to 31-03-2019 | Old Malda | 35% | 0 | ZP | Ongoing | |
2017-18 | Behargaon to Mahanagar - Package No. WB 11-217 | 01-04-2017 to 31-03-2018 | Gazole | 69% | 47.75 lakh | ZP | Ongoing | |
2017-18 | Behargram to Bilaikanagar - Package No. WB 11-222 | 01-04-2017 to 31-03-2018 | Gazole | 65% | 22.74 lakh | ZP | Ongoing | |
2017-18 | Saluka to Emamnagar - Package No. WB 11-230 | 01-04-2017 to 31-03-2018 | Gazole | 35% | 0 | ZP | Ongoing | |
2017-18 | Kushida to Gohila - Package No. WB 11-199 | 01-04-2017 to 31-03-2018 | Harishchandrapur-I | 40% | 0 | ZP | Ongoing | |
2017-18 | Haldibari to Ishadpur - Package No. WB 11-225 | 01-04-2017 to 31-03-2018 | Harishchandrapur-I | 30% | 0 | ZP | Ongoing | |
2017-18 | Parbhaluka to Illam Paschimpara - Package No. WB 11-212 | 01-04-2017 to 31-03-2018 | Harishchandrapur-II | 30% | 0 | ZP | Ongoing | |
2017-18 | Kaliachak to Salimpur - Package No. WB 11-198 | 01-04-2017 to 31-03-2018 | Kaliachak-I | 65% | 0 | ZP | Ongoing | |
2017-18 | Ghoshpara III to Gobindopur Purbatala - Package No. WB 11-226 | 01-04-2017 to 31-03-2018 | Kaliachak-II | 4% | 0 | ZP | Ongoing | |
2017-18 | Balufara to Kumbhira - Package No. WB 11-209 | 01-04-2017 to 31-03-2018 | Kaliachak-III | 75% | 183.94 lakh | ZP | Ongoing | |
2017-18 | 34 NH Connection Shimuldhab North to Baritola - Package No. WB 11-210 | 01-04-2017 to 31-03-2018 | Old Malda | 40% | 0 | ZP | Ongoing | |
2017-18 | NH-34 Narayanpur to Ranigarh - Package No. WB 11 -215 | 01-04-2017 to 31-03-2018 | Old Malda | 75% | 0 | ZP | Ongoing | |
2017-18 | SH Connection (Amzatpur) to Noldubi Bridge Colony - Package No. WB 11-228 | 01-04-2017 to 31-03-2018 | Old Malda | 55% | 0 | ZP | Ongoing | |
2017-18 | NH Connection (Chatian more Dubapara) to Char Laxmipur - Package No. WB 11-227 | 01-04-2017 to 31-03-2018 | Old Malda | 60% | 0 | ZP | Ongoing |